The Uptime Wind Energy Podcast
Vineyard Wind Sues GE, Ørsted Overhauls Its Board
37 min•21 april 2026
Om avsnittet
Vineyard Wind sues GE Renewables to block a walkout over $300M in withheld payments and defective blades. Plus Ørsted posts a $262M quarterly loss and shakes up its board.
Sign up now for Uptime Tech News, our weekly newsletter on all things wind technology. This episode is sponsored by Weather Guard Lightning Tech. Learn more about Weather Guard's StrikeTape Wind Turbine LPS retrofit. Follow the show on YouTube, Linkedin and visit Weather Guard on the web. And subscribe to Rosemary's "Engineering with Rosie" YouTube channel here. Have a question we can answer on the show? Email us!
Uptime316
Matthew Stead: [00:00:00] The Uptime Wind Energy Podcast brought to you by Strike Tape, protecting thousands of wind turbines from lightning damage worldwide. Visit strike tape.com And now your hosts.
Allen Hall: Welcome to the Uptime Wind Energy Podcast. I'm your host Allen Hall, and I'm here with Matthew Stead and Rosemary Barnes who are in Australia. Before we get too far into this episode, I would like to mention that the UK US relationship has been very tense recently, as you have seen in the, in the news articles and on television.
But there was one good news piece that just happened, which is the band Oasis just got inducted into the Rock and Roll Hall of Fame. So that is trying to mend those relationships, bring the UK and US back together. In at least a musical sense. So I know Rosemary was watching that closely as the votes were counted.
But, [00:01:00] uh, everybody in the UK is super thrilled about it as they should be. And all us Oasis fans can't wait for the induction ceremony. In fact, we're planning to go to Cleveland. They'll go watch it if we can. We shall see now onto more important information this week. Vineyard, wind and GE are not getting along.
And if you have been paying attention for the last two years, you would've noticed that there's been a couple of tense moments. Well, uh, that wind project is a little bit up in the air because vineyard wind has filed suit against GE renewables to stop the turbine maker from walking away after GE sent a termination notice.
Over a $300 million ish, uh, disagreement in unpaid bills. At the center of this dispute are defective blades, of course, that, uh, broke off in 2024 and caused a number of problems, uh, for GE and vineyard Wind is particularly a delay in the [00:02:00] project and ge having to fix pull blades off of turbines that were already installed and I think they ended up sending those back to France.
Reading the lawsuit, it seems like GE did not repair those blades. They replaced those blades because, uh, they may not have been able to repair them or maybe is the amount of time it's gonna take to repair them. You can repair almost anything made out of. Composite. Uh, but this is a big problem because, uh, if GE does walk away and they're talking about walking away from this project at the end of April, vineyard, wind believes that the turbines are not ready to be operated, and they don't have a way to operate those turbines.
They don't have the knowledge or the people because the people belong to GE that need to make some of these turbines operate. Even there's even some question about if all the turbines are operating at the required [00:03:00]handover requirements. This is unique because I don't think I've ever seen a wind turbine manufacturer leave before a wind site is finished.
It must have happened before, but. It does put both sides in quite a pinch. Right.
Rosemary Barnes: Can I just jump, jump back to, to something that you said, um, that you can repair almost anything when it comes to composites? I would say that that doesn't necessarily apply if your design was insufficient in the first place.
And I mean the design for manufacturing in this case, I think that the, like computer model design worked fine, but obviously it was not as easy to manufacture or as possible to manufacture. With the correct quality as what they expected. It can't have been so simple to just, just repair. That's, um, that's what I want to say.
Like it, it's obvious to me that if it was possible to repair, that would've been much easier than what they've ended up with, which I think is pretty foreseeable. Or most [00:04:00] engineers would probably have foreseen that if you, you know, put blades out there that, um, don't meet your. Standard, um, quality control acceptance criteria that, you know, the consequence of that would be that it would be more likely to fail.
So yeah, I think you can repair nearly anything on a standard blade that is possible to make correctly. But if you've got big quality problems, then it's not, it's, it's not easy and it's possibly not possible to, you know, just get, um, just get onto that in repair.
Matthew Stead: I, I think you're both right. Because it all comes down to economics.
So I think Alan's statement, you know, things can be repaired. It just comes back to economics, doesn't it?
Rosemary Barnes: U usually, yes. And like for your average, like if you've got a wind farm and you've got a blade with a big, a big repair, or you know, like a big defect right on the main laminate, that's gonna require, you know, like a huge repair, taking the blade down and keeping it down for, you know, like three months while you rebuild like 20 meters [00:05:00] of laminate.
Yes, that would be technically possible, but you wouldn't because it would be so expensive. So us usually, like in 99% of cases, that would be it. That it's not actually impossible to repair. It's just very hard. But, you know, in these really huge blades and, you know, um, bearing in mind that I don't, I don't know the specific quality problems that they face, but, you know, just from my knowledge of composites, you can say what the challenging areas would be, but you know, a really big blade is gonna have a really thick laminate and, um, composites don't like to have really thick laminates.
When they cure, it's usually an, an exothermic reaction, puts off heat, you know, like the temperature is changing and um, it works fine for thin laminates, but when it's really thick you can get hot spots and cold spots and maybe it's hard to get the resin to go all the way through evenly. But you know, imagine if you've got a really thick laminate and there's a chunk of it that just didn't get any resin in it.
How are you gonna repair that? Like, I wouldn't say impossible. I'm sure if the fate of the human race depended on it, then you would, you would make it work. But it's [00:06:00] certainly very close to impossible.
Matthew Stead: Economically, it does not make sense.
Rosemary Barnes: You would probably have to make a few inventions. Along the way to be able to make it work as well.
I think,
Allen Hall: I think I should read part of, and I don't like reading these lawsuits, but this is informative in a sense that it provides some relative background as to what Vineyard Wind is thinking in some of the contract details that are involved here. So in June 4th, 2021, this is directly from the lawsuit, uh, vineyard Wind entered into A TSA with GE renewables in which.
GE Renewables agreed to design, manufacture supply, install commission, and test the wind turbine generators for the vineyard wind project at a contract price of more than $1.3 billion. There you go. On the same day as an integral part of the commercial agreement, the parties entered into an SMA, uh, by which GE renewables agreed to maintain and service that wind turbine [00:07:00]generators for the first five years.
Of operations of the project and guarantee that all wind turbine generators will operate at a 97% of production availability. Uh, this guarantee is central, is a central component of the commercial viability of the Vineyard Wind Project. So I would say so, right. Uh, at present, all of the wind turbine generators on the project have been installed.
However, the wind turbine generators are not yet fully operational and are. Able to reduce power at only levels well below those intended under the contracts fundamental to the project's commitment to Massachusetts to achieve full commercial operation. The project requires repair, commissioning, and maintenance of GE renewables, 62 proprietary wind turbine generators, and their component parts work that only GE renewables knows how to perform.
So it sounds like Vineyard Wind has a five-year contract that GE ISS gonna operate these [00:08:00] turbines, and if they leave in a couple of weeks, vineyard wind really doesn't have a backup plan. They may have. Were planning on a plan five years down the road where they could operate 'em, but to operate those turbines immediately when they haven't, at least as.
Indicated here may not be fully commissioned to providing the right amount of availability. That's a huge problem for Vineyard. Huge.
Rosemary Barnes: It's interesting to me that they've decided to withhold some money that I think everyone agrees that they owe that money to ge. But then there's a dispute because Vineyard when says that GE owes them money for some other stuff That sounds like GE disputes.
Um, it's like if you have a problem. With your landlord, they always tell you, don't, don't withhold rent, because then they can, you know, that's, that's their out of the contract. Right? So it seems weird, like it's a relatively small amount compared to what vineyard wind is risking. So. It seems to me like, are they, is this a mistake from them?
Are they giving ge an out from this contract that's gonna be [00:09:00] really hard for them to meet? It might be that GE knows what it would cost to entirely fix the wind farm and have it producing the way that it should. But, you know, let's say in a worst case scenario, that means remaking every single blade in the um, in the wind farm.
At the, at the French factory, you know, like that could be your,...
The Uptime Wind Energy Podcast med Allen Hall, Rosemary Barnes, Yolanda Padron & Matthew Stead finns tillgänglig på flera plattformar. Informationen på denna sida kommer från offentliga podd-flöden.